This project was completed at the end of 2013 and involved a large temperature controlled distribution centre complete with a single storey office and yard areas.

The construction of this building included a traditional distribution centre format, consisting of; concrete floor slabs, precast tilt slabs, structural steel frame, PIR panels, and profiled metal cladding and roofing. 

This project was completed on time and further cemented our growing relationship as Bidvest’s contractor of choice and Q Constructions ability to deliver projects nationwide.


Compliance with Health, Safety & Environmental Standards:  YES

Compliance with Quality Standards:                                            YES

Completed On Time:                                                                      YES

Completed Within Budget:                                                             YES


Project Outline


  • Client: Bidvest NZ
  • Construction Period: May 2012 - November 2012
  • Construction Value: $4,200,000
  • Consultants: Peter Swan Limited
  • Referee: Phil Struckmann
    09 520 8056